The Civil Aviation Authority has opened a consultation on proposals that could take recoverable early costs for competing Heathrow expansion promoters to about £700 million from the beginning of 2025 to mid-2027.
CAP3331, published on 25 November 2026, considers further pre-Development Consent Order costs associated with Heathrow capacity expansion. It does not approve a third runway, authorise construction or create a presumption that costs after June 2027 will be recoverable.
The consultation covers Heathrow Airport Limited’s costs for the first half of 2027, alongside Heathrow West Limited’s costs for 2026 and January to June 2027. The CAA has made no final decision on the proposed additional cost recovery.
Heathrow Airport Limited has forecast early costs of up to £304 million for January to June 2027. The regulator says it can currently confirm proposed allowances totalling £256 million, comprising £169 million for Development Consent Order work, £47 million for programme management and £40 million for specified enabling work.
Under the proposals, Heathrow Airport Limited’s cap could rise to £304 million if further information is provided on land, property and central-terminal enabling costs.
Heathrow West Limited forecasts costs of approximately £46 million for 2026 and approximately £35 million for the first half of 2027. The CAA proposes a £46 million cap for the 2026 spending and an indicative, provisional cap of £35 million for the following six months.
Any spending allowed for recovery would still need to be eligible, justified, reasonably required and efficiently incurred. The CAA proposes to assess efficiency after expenditure has taken place through ex-post reviews.
Passengers planning airport journeys can compare pre-booked options with DM Airport Transfers.
The regulator has also proposed safeguards including spending caps, transparent reporting, independent scrutiny and information-sharing arrangements. It says these measures are intended to limit unnecessary duplication between the two promoters.
The CAA recognises that having two competing promoters could create pressure on design, delivery and costs, while also requiring protections against duplicated expenditure. Its July 2026 final decision separately covered specified early costs incurred by Heathrow Airport Limited in 2025-26 and Heathrow West Limited up to November 2025.
If the current package were implemented in full, the CAA estimates that combined early-cost recovery of about £700 million would equate to around 60p to 70p per Heathrow passenger journey if recovered over 20 years. Current average airport charges are about £26 per passenger.
Responses to the consultation are due by 5pm on Tuesday 12 January 2027. The CAA expects to publish a draft decision in spring 2027 and a final decision in summer 2027.
Separately, the Government is considering responses to its draft Heathrow Expansion National Policy Statement consultation. Any final policy statement would require parliamentary scrutiny and a vote before it could be designated.
Heathrow Airport Limited has said a 2035 runway opening is no longer credible and is assuming delivery would take roughly ten years from a Development Consent Order decision.
Thanks for visiting DM News! If you’ve got a question, a story tip, or anything you’d like to share, head over to DriverMatty.com — I love to hear from you. While you’re there, don’t forget to check out my other websites and social media channels.